The Lowdown on Calculated Allowances

What they are and how they work


By By Dennis Dixon November 11, 2016
This article first appeared in the November 2016 issue of Pro Remodeler.

In a construction contract, a calculated allowance is an amount determined by facts, figures, and experience to serve as a placeholder expense for as-yet unspecified items, such as light fixtures or cabinets. An allowance should be reasonable and match, as closely as possible, the quality the owner anticipates for the items it covers. Amounts that are much too high or low can cause problems when selections are actually made. For example, an allowance of $1,000 for floor covering for a 2,000-square-foot home works out to 50 cents per square foot or $4.50 per square yard. Even if you find something at that price, your clients will not be happy.

Define the Circumstances and Parameters

Using that example, here’s how I would calculate a more accurate allowance amount for carpet. First, I would list the rooms to be carpeted, along with the total square footage and a conversion to square yards.

Next, in addition to showing the total allowance price for carpet, I would show the installed cost per square yard.

To ensure that the allowance is reasonable, I use my judgment based on the quality of other finishes the client has chosen. If there’s time, I accompany the client to my floor-covering sub’s showroom. Sometimes they end up making a selection, but even if they don’t choose a particular carpet, I can tell whether they are gravitating toward the $25-per-yard samples or those at $40 per yard, and I can build the cost of that perceived preference into the allowance.    

Break It Down

My estimates usually contain 100 to 125 job-cost line item subcategories such as Carpet, Hardwood, Sheet Goods, Tile, etc.—the more “breakdown” the better the estimate. In most of these subcategories, allowances are among up to a dozen detailed line-item amounts. Overhead and profit for the whole subcategory, including allowances, are built into the contract price because all of those line items are summarized into one number for the parent category—“Flooring,” for example, or “Lighting” or “Painting.” 

Resolve Allowances With Change Orders

As luck would have it, when the client finally makes a product selection, the cost rarely matches the allowance amount. Whether it’s higher or lower, I handle the difference with a change order.

Following our example, let’s say that instead of choosing carpet at the allowance price of $25 per square yard, the client chooses more expensive $40-per-square-yard goods for the living room and both halls, but less expensive $20-per-square-yard carpet for the three bedrooms and the den. In that situation, I would issue a change order showing both the total installed invoice amount and the original allowance amount as lump sums. The difference would be either refunded to or paid by the owner.

These two adjustments are handled differently, and my contract spells that out. Except for small overages, which I typically let slide, when the client spends more than the allowance amount, my contract states that any “additional expenses” will be billed at cost plus a given percentage of the overage (typically 28 percent). So if, in our carpeting example, the client spends $1,000 more than the allowance, I would issue a change order showing the original allowance amount and the overage plus percentage.

When the client underspends, the change order subtracts the simple difference between the allowance and the actual cost from the contract price. Occasionally customers will ask why no fee or percentage is refunded. My answer really begins before we sign the contract, when I explain that I try to eliminate allowances to avoid the cost and aggravation. Unresolved allowances can affect the schedule and can even require changes to work that’s already been completed. Except for special circumstances, I don’t refund my fee because it compensates for the time I spend helping with the ultimate product selection, writing up the change order, and double-checking how allowance choices affect other work. 

My favorite clients are those who have been through a construction project before because they understand exactly what I’m talking about. And they are usually amazed at the level of detail I include and the systematic way in which I approach allowances and change orders. If you adopt some of these ideas, the same will be true for you.

Tags


written by

Dennis A. Dixon

Dennis A. Dixon is an author, contractor, and consultant. Look for his second edition of Finding Hidden Profits, to be published in late 2016.


Add new comment

Plain text

  • No HTML tags allowed.
  • Web page addresses and email addresses turn into links automatically.
  • Lines and paragraphs break automatically.
leaderboard2 - default

Related Stories

Pro's Picks: A Quick Install Composite Stone

This pro completed a high volume facelift project months ahead of schedule

Pella's New Debut Promises Faster, One-Person Window Installs

The window manufacturer promises 3.15x faster installation with its Steady Set system

Marvin Releases Switchable Privacy Glass Window

The privacy glass windows can be purchased from Marvin's Direct Glaze windows

Innovative Products: Window Shades That Create Natural Light

Wait, shouldn't window shades keep light out?

New Insulation Innovation Reshapes Our Thinking of Refrigeration

Whirlpool Corporation's latest innovation allows refrigerators to do more and be more

4 AI Tools for the Content Creating Contractor

Let artificial intelligence do the work

Innovative Products: A Whole-Home Energy Monitoring System

Homeowners can control their lighting, load control, and EV charging through one app

Pro's Picks: A Paperless Note-Taking Tablet

This remodeler recommends a tablet that makes note-taking and document organization easier

Building Materials Show Stability in 2023

Although supply chain bottlenecks have eased in recent months, shortages of some key materials persist.

Advertisement
boombox2 -
Advertisement
halfpage2 -
Advertisement
native1 -

More in Category




Advertisement
native2 -
Advertisement
halfpage1 -
Advertisement
leaderboard1 -